The machine you don't need yet

Before you buy capacity, find out how long your orders wait in front of the machine you think is the problem.

Most capital requests I see in mid-size plants start the same way. Orders are late, the queue in front of one machine is long, and the obvious answer is a second machine.

Sometimes that’s right. More often, the machine is busy for less of the day than anyone thinks, and the queue is long because work arrives in lumps.

Time the waits, not the work

Take twenty orders and write down, by hand, the time each one arrives at the machine, starts, and leaves. Do it for a week. You’ll usually find three things:

  • The machine runs well below what the capacity plan says
  • Orders arrive in batches tied to a schedule, not to demand
  • A lot of the wait is for something else: material, a setup, an inspection

What to do instead

If the machine runs at 70% and orders still queue, more capacity won’t fix the lumps. Smooth the arrivals first. A simple rule, like starting an order upstream only when there’s room in front of the machine, often does more than a second machine would.

Then measure again. If the machine really is full, you’ll buy it with numbers that justify it, and you’ll know exactly how much capacity you need.