Cutting a valve maker's lead time from 31 days to 13
- Client
- Family-owned valve manufacturer
- Sector
- Industrial valves
- Length
- 16 weeks
- Year
- 2026
- 13 daysQuoted lead time, from 31
- 93%On-time shipments, from 64%
- $1.2MSecond test cell no longer needed
Sample case study and figures, written for this template
The situation
A 140-person valve maker was quoting 31 days and missing a third of its ship dates. Sales had stopped promising dates at all, and the plant was running 400 hours of overtime a week to keep up.
The owners assumed the test cell was the constraint and were pricing a second one at $1.2 million.
What we did
Two weeks of measuring
We tagged 60 orders and timed every wait. The test cell ran at 70% of capacity; orders spent most of their time waiting for complete kits of parts before they could reach it.
Kitting moved upstream
Parts were picked for each order the day before assembly, not the hour before test. Two material handlers moved from the stockroom to a kitting bench next to the line.
A pull signal, not a schedule
Assembly started an order only when the test cell had an empty rack. A whiteboard and colored magnets replaced a daily spreadsheet that nobody trusted.
We were about to buy a machine we didn't need. Nell spent two weeks with a stopwatch and saved us the purchase.